Part of me is thrilled to no end that U.S. Embassy Beirut will, sooner or later, move out of its dinky and haphazard present facilities in East Beirut and into a big, purpose-built, New Embassy Complex. That is an occasion we've been waiting for ever since the previous embassy was destroyed by a suicide truck bomb in 1983, and then the East Beirut embassy annex itself was partially destroyed by a second suicide bomber in 1984.
1983? 1984? What a long time ago. How many current State Department employees had not yet been born in those years? That replacement embassy has been a long time coming.
Not to spoil my good mood, but what explains the insanely long time between the start of the project and its projected completion date?
As Diplopundit noted back in 2017, the project broke ground in April 2017, after a construction contract was awarded in December 2016, with completion anticipated in 2022. The design phase of the project was initiated in 2013 when a contract was awarded to Morphosis Architects.
I know nothing from architecture, but I can easily understand all the hate for a 15-story office building in which the elevators stop only at every third floor, where the employees can't have window shades to cut down on sun glare, where there is no heating or air conditioning (except in the manager's offices!), where there is no on-site cafe or restaurant for its 2,400 employees but there is a public plaza that attracted so much crime, trash, and drug use that it is now getting a big forbidding perimeter fence.
To be fair, Morphosis' San Francisco design has also gotten some awards, however, none of them came from the poor wretches who have to work there.
But enough said of the new embassy's architecture. I'm far more concerned about the project schedule.
Judging entirely from the embassy and Overseas Buildings Operations (OBO) press releases, it appears the plan was to spend five long years in the design phase - 2013 to 2017 - followed by another five long years in the construction phase. Project delays have now pushed the anticipated completion date out yet another year into 2023. But understand this: OBO intended to spend an entire decade to get that new embassy completed.
That is outrageous. I mean no offense to my good friends in OBO - and they really are my friends, I mean that sincerely - but WHAT WERE YOU THINKING when you approved a plan to build a new embassy in Beirut that would take an entire decade to complete? I'll put aside the matter of the 1+ billion dollar cost. Whatever happened to the sense of urgency that was the entire reason for the Capital Security Construction Program?
A plain utilitarian office and residential compound that took half as long to complete as one of Morphosis' eccentric masterpieces would have been a far better choice.
Embassy Beirut employees have been living and working in a ramshackle collection of buildings on a hastily-secured compound for 37 years and counting. Granted the security environment in Lebanon is not so acute now as it once was, but still, Hizbollah has pretty much free run of the place so speed really ought to have been a much higher priority for OBO than whatever design excellence whim-wham it is that Morphosis is bringing so very slowly.
What's not such a good thing is that the solicitation was dated March 28, 2013, which is just three weeks short of thirty years since the Beirut embassy bombing. That incident led to the Inman Commission and to the business of building Fortress Embassies which has gone on ever since. Now, thirty long years later, we might be close to finally building a Fortress in Beirut.
From the solicitation:
This will be a design-bid-build project. The resultant contract shall be fixed price. The estimated construction cost is $526.231 million.
The new Embassy compound will be constructed on U.S. Government-owned property located in Aoukar, approximately 11 km north of Beirut city neat the site of the existing U.S. Embassy compound. The complex of buildings will be in the range of 78,636 gross square meters in area and will include a new Chancery, General Services Office/support buildings, parking structure, TDY lodging facility, Marine Security Guard Quarters (MSGQ), Chief of Missions Residence (CMR), Deputy Chief of Missions Residence (DCMR), Staff Housing, Compound Access Control (CAC) facilities, RSO Annex, Utility Building, Community Center, and vehicular/pedestrian screening facilities. The project site is approximately 17.8 hectare (43 acres) located on a steep hillside in a neighborhood of residential and light commercial uses. The land slopes east to west with a topographic change of approximately 100 meters. This project will be designed and constructed to achieve, as a goal, a LEED Silver rating.
By the way, the sketch I inserted above is not connected to the present solicitation. It is from the very first attempt to build a new U.S. Embassy in Beirut, back in 1957. That project was suspended during the Lebanese Civil War of 1958. History keeps repeating, huh?